The Class 2 estimate is the cost baseline for project control — built on detailed quantities, market labor rates, and equipment rental data. This is the estimate you manage against.
How Kpex implements Class 2 following AACE 18R-97
Kpex 2G guides the cost engineer through every step of the Class 2 workflow — from scope input to indexed, location-adjusted output — enforcing the AACE recommended methodology at each stage. The platform validates inputs, applies the correct indices automatically, and generates a documented Basis of Estimate aligned with AACE 18R-97.

The Class 2 Control Estimate is the cost baseline against which project execution is managed. Prepared when engineering is 30–70% complete, it achieves an expected accuracy of −10% to +20% — tight enough to serve as the financial benchmark for earned value management (EVM) and change control.
The defining feature of a Class 2 estimate is that it is resource-loaded: every quantity is priced using actual market rates for labour crews, construction equipment rental, and purchased materials — not factors or ratios. Nothing is estimated by analogy at Class 2.
| Dimension | Class 3 | Class 2 |
|---|---|---|
| Engineering complete | 10–40% | 30–70% |
| Quantity basis | Engineered + interpolated | Detailed takeoff from IFC drawings |
| Labour pricing | % of direct cost | Crew rates × productivity × hours |
| Equipment rental | Included in factor | Day/month rates from Z.3 database |
| Contingency | 10–20% | 5–15% |
| Primary use | Budget appropriation | Contract award, EVM baseline, change control |
The four-level WBS structure from Class 3 is inherited. However, quantities are now re-taken from Issued for Construction (IFC) or Issued for Review (IFR) drawings, replacing any interpolated or parametric quantities used at Class 3.
For each L4 WBS item, perform a full material takeoff:
Each work package is priced using labour crew compositions and rates from Kpex Module Z.2:
Construction equipment (cranes, excavators, concrete pumps, air compressors, generators) is priced using day or month rates from Kpex Module Z.3, combined with estimated utilisation days per work package.
Bulk materials (pipe, fittings, cable, concrete, rebar, structural steel) are priced using current vendor quotations or market indices. Material price escalation from order date to delivery is applied using the Z.5 CAI time-adjustment factors.
At Class 2, indirect costs are detailed line by line — not applied as a percentage. The construction management team, site facilities, consumables, subcontractor mobilisation, testing and commissioning, and owner's project management costs are all explicitly scoped and priced.
If the labour and equipment rate database is on a different country basis than the project location, apply Z.4 LFI. Apply Z.5 CAI for escalation to the project's mid-point of construction (weighted average of cost commitments over the schedule).
At Class 2, contingency is determined through probabilistic risk analysis — Monte Carlo simulation using identified risk events, probability distributions, and cost impacts. The result is a P50 (expected value) and P80 (high-confidence) cost estimate, with contingency equal to P80 minus the deterministic base.
| Module | Data Provided | Applied At |
|---|---|---|
| Z.2 — Labor Rates | Crew compositions & all-in rates by trade/country | Every labour-loaded WBS item |
| Z.3 — Rental Equipment | Day/month rates by equipment category | Construction plant & equipment WBS items |
| Z.4 — LFI | Location factors for 196 countries | Estimate header — adjusts all direct costs |
| Z.5 — CAI | CEPCI / ENR time-based escalation | Estimate header — escalates to execution year |
| Z.6 — PDRI | Project Definition Rating Index score | Informs contingency & risk register |