Class 1 is the gold standard of cost estimation — prepared when the project is fully defined, all vendor quotes are received, and every material quantity is confirmed. No shortcuts, no factors.
How Kpex implements Class 1 following AACE 18R-97
Kpex 2G guides the cost engineer through every step of the Class 1 workflow — from scope input to indexed, location-adjusted output — enforcing the AACE recommended methodology at each stage. The platform validates inputs, applies the correct indices automatically, and generates a documented Basis of Estimate aligned with AACE 18R-97.

The Class 1 Definitive (or Check) Estimate represents the highest possible level of cost certainty achievable before physical construction begins. Prepared when engineering is 65–100% complete, it achieves an expected accuracy of −5% to +10% (some references cite ±5–8%).
A Class 1 estimate is used for:
At Class 1, there are no factors, no ratios, no analogies. Every cost element is derived from one of three definitive sources:
Verify that all engineering deliverables required for full takeoff are available and at the correct revision status:
Every item in the material control system must be counted and quantified from engineering documents. This is typically performed by a dedicated takeoff team using CAD-integrated MTO software (Smart 3D, PDMS, Tekla, etc.) cross-checked manually for critical lines.
All purchased equipment, bulk materials (pipe, fittings, cable, structural steel, instrumentation) and package units must have received at minimum two competitive vendor quotations, with the basis of pricing clearly defined (ex-works, delivered to site, duty paid, etc.).
Divide construction scope into sub-contract packages consistent with the planned contracting strategy. Issue enquiries, receive bids, and level bids for scope and commercial terms. Use the lowest technically compliant bid for the estimate.
For self-performed work (if any), apply definitive all-in crew rates from the signed or anticipated labour agreements. All productivity adjustments (shift schedule, weather, site conditions, labour availability) must be formally documented and justified.
The indirect cost estimate at Class 1 is derived from a detailed staffing plan — named or functional positions, for defined durations, at confirmed salary/rate levels. No indirect cost percentage factors are acceptable.
Apply escalation from the quotation validity date to the expected purchase order date and, for labour, to the mid-point of that work's execution window. Use project-specific escalation forecasts where possible; fallback to published indices (CEPCI, ENR CCI) for materials.
At Class 1, contingency is narrow — typically 3–8% of TIC — and is supported by a formal Quantitative Risk Analysis (QRA). Remaining risks are specific, identified, and quantified. Management Reserve is minimal.
| Dimension | Class 2 | Class 1 |
|---|---|---|
| Engineering | 30–70% | 65–100% |
| Material pricing | Market rates / budget quotes | Firm vendor quotations |
| Labour pricing | DB crew rates × productivity | Signed labour agreement or sub-bid |
| Indirects | Detailed line-by-line or % | Full staffing plan, named positions |
| Accuracy | −10% / +20% | −5% / +10% |
| Contingency | 5–15% | 3–8% |
| Time to prepare | 4–10 weeks | 6–16 weeks |
When an EPC contractor bids on a lump-sum contract, they commit to a fixed price. Their internal Class 1 estimate is the basis for that commitment. The contractor carries all cost risk beyond the stated contract allowances. Any gap between the Class 1 estimate and the submitted bid price represents the contractor's intended margin.
Before evaluating bids, sophisticated owners prepare an Independent Cost Estimate at Class 1 level. Bids that deviate more than ±10–15% from the ICE trigger detailed scope alignment reviews. This is standard practice in regulated industries (nuclear, government infrastructure) and large-scale O&G projects.
When a scope change is disputed, a Class 1 estimate prepared by a qualified cost engineer — with full documentation, MTO, and pricing evidence — constitutes defensible evidence in arbitration or litigation. AACE Recommended Practice 29R-03 addresses claims methodology directly.
While Class 1 estimates are built on project-specific data (vendor quotes, sub-bids, IFC drawings) rather than database lookups, Kpex supports the process through: